References

Below is a list of some of the projects that we carried out:

  • Sewer system in PAWŁOWICE ŚLĄSKIE
    HDPE Manholes of diameters DN 1000 DN 800 and DN 400 mm.
  • Sewer system in DANKOWICE
    HDPE Manholes of diameters DN 800 mm.
  • Sewer system in WILAMOWICE - STARA WIEŚ
    HDPE Manholes of diameters DN 800 mm.
  • Sewer system in SKOCZÓW
    HDPE Manholes of diameters DN 800 and DN 400 mm.
  • Sewer system at the Meat Processing Plant STARPECK in BIELSKO BIAŁA
    HDPE Manholes of diameters DN 1000 and DN 800 mm and grease traps.
  • Sewer system in GOCZAŁKOWICE
    HDPE Manholes of diameters DN 400 mm.
  • Sewer and storm water drainage system at the Meat Processing Plant H. KANIA in PSZCZYNA
    Installation of pipeline of diameters range from DN 160 to DN 400 mm, manufacturing and installation of HDPE manholes of diameters DN 400, DN 800, DN 1000.
  • Sewer system repair in ŁAZISKA GÓRNE
    HDPE modules for trenchless repair of pipeline of diameters DN 250, DN 315, DN 450.
  • Sewer system
    Ring road of ul. Andersa in BIELSKO BIAŁA – HDPE manholes DN 1200 and DN 1600.
  • Manifold VIII in ŁÓDŹ
    Inspection chambers.
  • Sewer system in MAKÓW PODCHALAŃSKI
    HDPE manholes of diameters DN 1000 and DN 400 mm.
  • Bridge construction on the Soła River in ŻYWIEC, storm water drainage system
    HDPE manholes DN 1000 mm.
  • Sewer system in RYBNIK WIELOPOLE
    HDPE manholes DN 1200 mm.
  • Sewer system in WISŁA MAŁA
    HDPE manholes DN 800 mm.
  • MOKATE in USTROŃ and in ŻORY
    HDPE Sewage pumping stations and manholes.
  • Sewer system in KĘTY
    HDPE manholes DN 800 mm.
  • Sewer system in MIKOŁÓW KAMIONKA
    HDPE manholes DN 1200 mm.
  • Sewer system, delivery pipeline in ŚWINOUJŚCIE
    Butt fusion of HDPE pipes of diameter range DN 200 - DN 450 mm.
  • Sewer system repair and renovation at a residential building located at the Military Unit in PSZCZYNA
    HDPE manholes DN 1000 and DN 1200 mm.
  • Trunk water main BOBREK-CHEŁMEK of length of approx. 1 km
    Butt fusion of PE 100 pipes of a diameter 630 mm.
  • Trunk water main in CHEŁMEK of length of approx. 1.2 km
    Fusion welding of PE 100 pipes of a diameter 630 mm.
  • Wastewater treatment Plant "Ruptawa" renovation and repair in JASTRZĘBIE ZDRÓJ
    Manufacturing of HDPE fittings for process pipelines and fusion welding of HDPE pipelines of diameter range DN 32 - DN 1350 mm.
  • Salt water pipeline makeover DN 400 mm in PAWŁOWICE PNIÓWEK
    HDPE delivery pipeline DN 400 mm PN 16 of length 832 lin. m., construction of 3 dewatering chambers DN 1000 mm, chamber construction - DN 1200 mm with a gate valve and an air vent, construction of 2 air vent chambers - DN 600 mm.
  • Salt water pipeline makeover DN 500 mm of the "OLZA" manifold of length 400 lin. m. in RYBNIK BOGUSZOWICE.
  • HDPE trunk water main at the Meat Processing Plant in PUŁAWY of length of approx. 1000 lin. m.
    Fusion welding of HDPE pipes DN 500 and DN 250 mm.
  • HDPE trunk water main in ŁĘCZNA (hospital construction site) of length of approx. 400 lin. m.
    Fusion welding of HDPE pipes DN 160 and DN 90 mm.
  • HDPE trunk water main in OŻARÓW of length of approx. 450 lin. m.
    Fusion welding of HDPE pipes DN 500 mm.
  • Swimming pool water treatment system at "SIELEC" in SOSNOWIEC
    Fusion welding of HDPE process pipelines DN 50 - DN 400 mm.
  • Swimming pool water treatment system at the JAWORZNO Power Plant
    Fusion welding of HDPE process pipelines DN 110- DN 280 mm.
  • Industrial water supply pipeline at the ŁAZISKA Power Plant
    Fusion welding of HDPE pipes DN 450 mm of total length of approx. 2000 lin.m.
  • Sand mine MACZKI-BÓR
    Fusion welding and welding of HDPE pipes DN 400 mm.
  • Match Manufacturing Plant in CZECHOWICE DZIEDZICE
    HDPE units for match impregnation and a free standing tank for wastewater.
  • Bicycle manufacturing plant "Apollo" in CZECHOWICE DZIEDZICE
    PVDF coating for a chromium bath.
  • Water supply systems and process pipelines at the Wastewater Treatment Plant in Kraków Płaszów
  • Water supply systems and process pipelines at Enersys sp. z o.o.
  • Drainage system of the Śląski stadium
  • Przedsiębiorstwo Gospodarki Wodnej i Rekultywacji S.A. (Water and Sewage Management Enterprise) in Jastrzębie Zdrój water system construction on the Olza River;
  • Chemical process pipelines at the Tychy Brewery;
  • General Motors Poland Sp. z o.o. Gliwice branch,
    Pipeline installation
  • Fiat Auto Poland
    Installation of pipelines
  • Swimming pools
    Tanks of a volume range from 3m3 to 34m3
  • Sewer system at the main square in Pszczyna;
  • Henkel installation of pipelines
  • HDPE cooling water system for a cooling plant 500m3/h at the Walcownia Metali "Dziedzice" S.A.
  • PE100 Fittings of a diameter 710mm and 500mm, for the pipeline makeover at the International Paper Sp. z o.o.
  • HDPE water supply pipeline diversion HDPE
    of a diameter 400mm with appurtenances at the construction site of water retention ponds in Chrzanów Sosnowa Góra
  • HDPE External flow and collector pipeline
    of a diameter 500mm and 400mm with appertunances at the construction site of water retention ponds in Chrzanów Kąty
  • Design and manufacture of a 150l/s oil/water separator and a settling tank of 10m3 (2008)
  • Polypropylene water distribution systems of a diameter range from 160mm to 315mm (2008).
  • HDPE pipeline fusion welding of a diameter 250mm in Chrzanów Kroczymiech
  • PE tank of a diameter 2600mm and length 5770mm
  • Water supply pipeline in PP pipes of a diameter range from 20 to 50 and total length of 830 lin.m. at the Wastewater Treatment Plant Płaszów II in Kraków
  • PVC and cast iron pipe sewer system installation of a diameter range from 50mm to 160mm and total length of 195 lin.m. at the Wastewater Treatment Plant Płaszów II in Kraków
  • Central heating system installation
    at the Wastewater Treatment Plant Płaszów II in Kraków
  • HDPE pipe PIX dosing station
    of a diameter 32mm – 2522 lin.m., PVC of a diameter 25mm – 45 lin. m. at the Wastewater Treatment Plant Płaszów II in Kraków
  • HDPE pipe methanol delivery pipeline of a diameter 125mm -321 lin.m., of a diameter 110mm -26 lin.m., of a diameter 75mm -130 lin. m. at the Wastewater Treatment Plant Płaszów II in Kraków
  • PIX dosing station and storage tanks, PVC pipes of a diameter 110mm, 90mm, 50mm, 20mm complete with PVC fittings for gluing, shut-off valves for gluing and a PVC settling filter of a diameter 20mm at the Wastewater Treatment Plant Płaszów II in Kraków